Magnavale Easton Making Substantial Progress – Pallet Cranes Being Fitted

We are pleased to announce we have made a £130 million investment into our new cold storage development in Easton, Lincolnshire. Our team has been diligently working on the construction of Europe’s most efficient temperature-controlled storage facility since breaking ground in September 2022. We are happy to report that we have achieved many of our development milestones and some of the aspects of the project have already been completed.

Magnavale Easton Construction

McClaren has finished the main concrete slab, and the low bay has now been clad. In addition, the steelwork for the staircase in the new office block has been completed.  We have now started constructing the automation in the low bay as well as the high bay cladding. An essential component the pallet crane system, responsible for the automated handling of pallets into the racking system, is currently being erected.

Along with the installation of the electrical infrastructure and the fire suppression system, we are constructing the refrigeration and oxygen reduction plantrooms, crucial components for what will be Europe’s most efficient cold store.

We are delighted with the progress of the development, and we are confident that we will complete construction in Q4 2024.

To learn more about Magnavale Easton Phase II click here, or to enquire about storage solutions, Please contact us below.

Magnavale Easton Construction

More on Cold Storage

Shortening the Cold Chain

Shortening the Cold Chain

As a leading provider of temperature-controlled storage and value-added services, we have an understanding of the challenges food...

Contact Us

Head Office:
Magnavale Ltd, Park Road,
Holmewood Industrial Park,
Chesterfield, S42 5UY

01246 854999