Construction Update: Magnavale Chesterfield Cold Store Extension
We currently have various exciting construction projects taking place across our network of temperature-controlled storage facilities, one of which is the development at Magnavale Chesterfield.
We are excited to share that we have made great progress on the construction. The steel framework is now complete, and the installation of insulated wall and roof panels is nearing completion as well.
In September, we’ll be finishing the roof membrane and intumescent painting of the new steelwork. Work will also begin on the small plant rooms and internal services like electrics, plumbing, and refrigeration.
The expansion remains on track for completion in late 2024, which will add 25,000 additional pallet positions to the existing 44,000 at Chesterfield. This increased capacity will allow us to better serve the needs of our valued customers and will open the opportunity for other businesses to come onboard with us as new partners.
As always, we aim to provide sustainable cold storage solutions that reduce environmental impact and drive operational efficiency. The Chesterfield expansion is a key part of this commitment, and we’re excited to see it taking shape.
If you are interested in cold storage solutions or any of our value-added services, please enquire below.
More News & Articles
Magnavale: Reflecting on 2022
As we approach the end of the year, we wanted to reflect on some of the progress we’ve made and the incredible work done by each of the...
Rounding up the Frozen Food & Cold Chain Trends of 2022
At the beginning of 2022, we discussed the frozen food trends of 2021 and made our predictions of how the frozen food aisles and cold...
Construction Underway at Magnavale Easton
During 2021, we announced that we secured the planning and funding to construct a fully automated 101,000 pallet cold storage facility...
Contact Us
Head Office:
Magnavale Ltd, Park Road,
Holmewood Industrial Park,
Chesterfield, S42 5UY